You are here:HOME >POLICY >ROADS AND TRANSPORT > 2002 ROADS CONGRESS > Report of Public Inquiry on Mechanisms

National Local Roads Congress 2002

Presentation by Professor Allan Layton

Final Report of Public Inquiry on Mechanisms to Fund Queensland's Road and Transport Infrastructure

Contents

Objectives of Inquiry

Identify funding alternatives to satisfy Queensland's road and transport infrastructure needs.

Inquiry Process and Timeline

January 17Inquiry Launch
February 10Background Paper released and public submissions called
March 15Closing date for submissions and Discussion Paper released
March 22-27*Public Hearings conducted
April 8-15Community Survey carried out
May 2Interim Report released, presentation at QLD Road and Transport Forum, and final feedback sought
May 31Final Report handed to LGAQ

* Large number of individual stakeholder meetings were also conducted during the period Feb 10 March 21.

Funding Options

Inquiry accepted that a reprioritisation of expenditure (from existing sources) in favour of transport infrastructure was unlikely.

Therefore Inquiry sought suggestions for new funding sources.

Alternatives suggested in submissions, stakeholder meetings and public hearings included:

Commonwealth Funding

Thus:

Recommendation 1:

Queensland Fuel Subsidy Scheme (QFSS)

Thus:

Recommendation 2:

Table 2.7: Congestion Costs in Capital Cities - 1995 to 2015

CityCongestion cost 1995 $billionCongestion cost 2015 $billionCongestion cost/capita 1995Congestion cost/capita 2015
Sydney$6.0$8.8$1600$2000
Melbourne$2.7$8.0$840$2100
Brisbane$2.6$9.3$1800$4600
Adelaide$0.8$1.5$740$1500
Perth$0.6$1.9$480$1900

Source: BTE 1999; (congestion cost is value of excess travel time and extra fuel use relative to free flow conditions)

Private Sector Involvement

Thus:

Recommendation 3

PPPs should be encouraged by the State Government as one mechanism to accelerate the provision of key elements of the road and transport system, particularly in SEQ.

User Pay Mechanisms - Toll Roads

Therefore:

Recommendation 4:

User Pay Mechanisms - Cordon Pricing

Therefore:

Recommendation 5:

User Pay Mechanisms - Parking Levies

Thus:

Recommendation 6:

Public Sector Borrowing

Thus:

Recommendation 7:

Impact/Development Fees

Thus:

Recommendation 8:

Table 5.9: Summary of Proportion Indicating Opposition to Option

LocationBrisbane metropolitonOuter metropolitonProvincialRuralTotal
Greater use of debt23.6%20.6%33.6%43.1%28.8%
Toll roads if alternative untolled route (b)26.1%20.5%45.7%30.6%28.8%
Congestion charges33.1%24.8%50.0%20.9%31.1%
Remove fuel subsidy, with rego reduction and rest on roads and transport27.4%33.2%35.0%44.0%33.3%
Greater private participation38.0%35.8%39.3%58.3%42.3%
Greater use of toll roads (a)45.0%44.7%55.0%42.2%45.7%
Electronic user charges50.6%44.3%46.5%52.9%49.3%
Remove fule subsidy - all spent on roads (a)47.8%50.6%47.9%58.2%50.7%

(a) initial question prior to supplementary question (b)

Conclusion

Ultimately the public must be prepared to pay the price to obtain a road and transport system which meets its needs.

Queenslanders have a choice. They can choose to maintain the lowest taxes, fuel prices and per capita debt in Australia. However, they must also be prepared to accept that a consequence of this choice may then be an inadequate road and transport system.

Alternatively, they can choose to support the financing of major road and transport infrastructure upgrades using some suitable combination of measures such as have been outlined in this report.